Maine Statutes
§ 35-A §3495 — Standards
Maine § 35-A §3495
JurisdictionMaine
Title 35-APUBLIC UTILITIES
Part 3ELECTRIC POWER
Ch. 34-DSOLAR ENERGY DEVELOPMENT DECOMMISSIONING
This text of Maine § 35-A §3495 (Standards) is published on Counsel Stack Legal Research, covering Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Me. Rev. Stat. tit. 35-A, § 35-A §3495 (2026).
Text
An environmental permitting entity shall approve a decommissioning plan whenever it finds the following:
1.Successful decommissioning.
The plan, if implemented, will result in successful decommissioning of the solar energy development, including the restoration of farmland sufficient to support resumption of farming or agricultural activities;
2.Financial assurance.
The person identified in the plan as responsible for decommissioning demonstrates financial assurance, in the form of a performance bond, surety bond, irrevocable letter of credit or other form of financial assurance acceptable to the environmental permitting entity, for the total cost of decommissioning; and
3.Update.
The plan requires the financial assurance be updated 15 years after approval of the plan and no less freque
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
PL 2021, c. 151, §1 (NEW). PL 2021, c. 151, §2 (AFF).
Nearby Sections
15
§ 35 §1-A
Public Advocate§ 35 §1001
Fences; liability for injuries§ 35 §1002
Line fences built on notice of abutter§ 35 §101
Special privileges forbidden§ 35 §102
Unjust discrimination§ 35 §103
Rebates§ 35 §104
Affiliated interests§ 35 §104-A
Insider transactions§ 35 §105
Utility depositsCite This Page — Counsel Stack
Bluebook (online)
Maine § 35-A §3495, Counsel Stack Legal Research, https://law.counselstack.com/statute/me/35-A%20%C2%A73495.