An environmental permitting entity shall approve a decommissioning plan whenever it finds the following:

1.Successful decommissioning. The plan, if implemented, will result in successful decommissioning of the solar energy development, including the restoration of farmland sufficient to support resumption of farming or agricultural activities;
2.Financial assurance. The person identified in the plan as responsible for decommissioning demonstrates financial assurance, in the form of a performance bond, surety bond, irrevocable letter of credit or other form of financial assurance acceptable to the environmental permitting entity, for the total cost of decommissioning; and
3.Update. The plan requires the financial assurance be updated 15 years after approval of the plan and no less freque

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

PL 2021, c. 151, §1 (NEW). PL 2021, c. 151, §2 (AFF).

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maine § 35-A §3495, Counsel Stack Legal Research, https://law.counselstack.com/statute/me/35-A%20%C2%A73495.