§ 35-A §3494 — Decommissioning plan

Maine § 35-A §3494
JurisdictionMaine
Title 35-APUBLIC UTILITIES
Part 3ELECTRIC POWER
Ch. 34-DSOLAR ENERGY DEVELOPMENT DECOMMISSIONING

This text of Maine § 35-A §3494 (Decommissioning plan) is published on Counsel Stack Legal Research, covering Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Me. Rev. Stat. tit. 35-A, § 35-A §3494 (2026).

Text

A decommissioning plan must:

1.Decommissioning. Provide for the decommissioning of a solar energy development. For any portion of the development located on land classified as farmland any time within 5 years preceding the start of construction of the development, the plan must provide for the restoration of that farmland upon decommissioning sufficient to support resumption of farming or agricultural activities;
2.Grading and revegetation of earth. Provide for the grading and revegetation of all earth disturbed during construction and decommissioning, except for areas already restored; and
3.Financial capacity. Include demonstration of current and future financial capacity, which must be unaffected by the owner's or operator's future financial condition, to fully fund decommissioning i

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

PL 2021, c. 151, §1 (NEW). PL 2021, c. 151, §2 (AFF).