§ 35-A §3210-C — Capacity resource adequacy
1.Definitions.
As used in this section, unless the context otherwise indicates, the following terms have the following meanings.
2.Policy.
It is the policy of this State:
3.Commission authority.
The commission may direct investor-owned transmission and distribution utilities to enter into long-term contracts for:
3-A.
Regional coordination.
If the commission determines that the likely benefits to ratepayers in the State will exceed the likely costs, the commission may coordinate with one or more states to procure, through long-term contracts or other mechanisms, transmission capacity, capacity resources, renewable energy credits or clean energy credits.
4.Priority of capacity resources.
In selecting capacity resources for contracting pursuant to subsection 3, the commission shall apply
Free access — add to your briefcase to read the full text and ask questions with AI
Maine § 35-A §3210-C (Capacity resource adequacy) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
PL 2005, c. 677, §C1 (NEW). PL 2007, c. 293, §§1-4 (AMD). PL 2007, c. 575, §§2-5 (AMD). PL 2007, c. 656, Pt. B, §§1-5 (AMD). PL 2009, c. 415, Pt. A, §§21-23 (AMD). PL 2009, c. 518, §§1-6 (AMD). PL 2009, c. 542, §6 (AMD). PL 2011, c. 273, §§1, 2 (AMD). PL 2011, c. 273, §3 (AFF). PL 2011, c. 413, §§2, 3 (AMD). PL 2013, c. 369, Pt. A, §2 (AMD). PL 2013, c. 424, Pt. A, §20 (AMD). PL 2013, c. 454, §1 (AMD). PL 2017, c. 134, §§1, 2 (AMD). PL 2019, c. 476, §2 (AMD). PL 2023, c. 77, §7 (AMD). PL 2023, c. 516, Pt. B, §49 (AMD). PL 2025, c. 386, §§13-21 (AMD). PL 2025, c. 476, Pt. A, §10 (AMD).
Nearby Sections
15
§ 35 §1-A
Public Advocate§ 35 §1001
Fences; liability for injuries§ 35 §1002
Line fences built on notice of abutter§ 35 §101
Special privileges forbidden§ 35 §102
Unjust discrimination§ 35 §103
Rebates§ 35 §104
Affiliated interests§ 35 §104-A
Insider transactions§ 35 §105
Utility deposits