Maine Statutes

§ 35-A §315 — Transmission and distribution utility line extension construction

Maine § 35-A §315
JurisdictionMaine
Title 35-APUBLIC UTILITIES
Part 1PUBLIC UTILITIES COMMISSION
Ch. 3RATES OF PUBLIC UTILITIES

This text of Maine § 35-A §315 (Transmission and distribution utility line extension construction) is published on Counsel Stack Legal Research, covering Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Me. Rev. Stat. tit. 35-A, § 35-A §315 (2026).

Text

1.Definitions. As used in this section, unless the context otherwise indicates, the following terms have the following meanings.
2.Line extension charge. Amounts charged by a transmission and distribution utility serving more than 500,000 retail customers for a line extension are governed by this subsection.
3.Cost recovery. Any cost associated with construction of a line extension that is not recovered by a transmission and distribution utility serving more than 500,000 retail customers through the charges established in accordance with subsection 2 must be borne by the utility and may not be recovered in rates.
4.Fees for make-ready work. A transmission and distribution utility serving more than 500,000 retail customers may charge a customer taking polyphase service the actual costs

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

PL 2011, c. 484, §1 (NEW).