Maine Statutes
§ 35-A §315 — Transmission and distribution utility line extension construction
Maine·Title 35-A PUBLIC UTILITIES·Part 1 PUBLIC UTILITIES COMMISSION·Ch. 3 RATES OF PUBLIC UTILITIES
1.Definitions.
As used in this section, unless the context otherwise indicates, the following terms have the following meanings.
2.Line extension charge.
Amounts charged by a transmission and distribution utility serving more than 500,000 retail customers for a line extension are governed by this subsection.
3.Cost recovery.
Any cost associated with construction of a line extension that is not recovered by a transmission and distribution utility serving more than 500,000 retail customers through the charges established in accordance with subsection 2 must be borne by the utility and may not be recovered in rates.
4.Fees for make-ready work.
A transmission and distribution utility serving more than 500,000 retail customers may charge a customer taking polyphase service the actual costs
Free access — add to your briefcase to read the full text and ask questions with AI
Maine § 35-A §315 (Transmission and distribution utility line extension construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
PL 2011, c. 484, §1 (NEW).
Nearby Sections
15
§ 35 §1-A
Public Advocate§ 35 §1001
Fences; liability for injuries§ 35 §1002
Line fences built on notice of abutter§ 35 §101
Special privileges forbidden§ 35 §102
Unjust discrimination§ 35 §103
Rebates§ 35 §104
Affiliated interests§ 35 §104-A
Insider transactions§ 35 §105
Utility deposits