Maine Statutes
§ 35-A §3147 — Integrated grid planning
1.Definitions.
As used in this section, unless the context otherwise indicates, the following terms have the following meanings.
2.Priorities identified; stakeholder input.
Beginning November 1, 2022, then every 5 years thereafter, the commission shall initiate a proceeding to identify the priorities to be addressed in a filing by a covered utility regarding a grid plan that will assist in the cost-effective transition to a clean, affordable and reliable electric grid. The commission shall hold technical conferences or stakeholder workshops before the filing to identify priorities, assumptions, goals, methods and tools that will assist the covered utility in developing a grid plan.
3.Commission order.
At the conclusion of the technical conferences and stakeholder workshops held under su
Free access — add to your briefcase to read the full text and ask questions with AI
Maine § 35-A §3147 (Integrated grid planning) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
PL 2021, c. 702, §8 (NEW). PL 2025, c. 293, §§2-5 (AMD). PL 2025, c. 293, §8 (AFF).
Nearby Sections
15
§ 35 §1-A
Public Advocate§ 35 §1001
Fences; liability for injuries§ 35 §1002
Line fences built on notice of abutter§ 35 §101
Special privileges forbidden§ 35 §102
Unjust discrimination§ 35 §103
Rebates§ 35 §104
Affiliated interests§ 35 §104-A
Insider transactions§ 35 §105
Utility deposits