Maine Statutes

§ 35-A §3102 — Recovery of cost of canceled or abandoned electric generating facility or transmission or distribution plant

Maine § 35-A §3102
JurisdictionMaine
Title 35-APUBLIC UTILITIES
Part 3ELECTRIC POWER
Ch. 31GENERAL PROVISIONS

This text of Maine § 35-A §3102 (Recovery of cost of canceled or abandoned electric generating facility or transmission or distribution plant) is published on Counsel Stack Legal Research, covering Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Me. Rev. Stat. tit. 35-A, § 35-A §3102 (2026).

Text

1.Determining rate-making treatment. In determining the rate-making treatment for a utility's investment in a canceled or abandoned electric generating facility or transmission or distribution plant, the commission shall balance the interests of the utility and ratepayers in a just and reasonable manner in each individual case. The commission may not permit a utility to recover in rates any costs incurred imprudently in relation to an investment in a canceled or abandoned electric generating facility or transmission or distribution plant.
2.Canceled or abandoned generating facility or transmission or distribution plant. As used in this section, the term "canceled or abandoned generating facility or transmission or distribution plant" means any electric generating facility or transmission

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

PL 1987, c. 141, §A6 (NEW). PL 1987, c. 490, §A4 (AMD). PL 1999, c. 398, §A43 (AMD). PL 1999, c. 398, §§A104,105 (AFF).