Maine Statutes

§ 10 §1116 — Retainage

Maine·Title 10 COMMERCE AND TRADE·Part 3 REGULATION OF TRADE·Ch. 201-A CONSTRUCTION CONTRACTS
1.Payment. If payments under a construction contract are subject to retainage, any amounts retained during the performance of the contract and due to be released to the contractor upon completion must be paid within 30 days after final acceptance of the work.
2.Retainage for subcontractors. If an owner is not withholding retainage for a subcontractor's work, a contractor may withhold retainage from its subcontractor or material supplier in accordance with their agreement. The retainage must be paid within 30 days of final acceptance of the work.
3.Payment of retainage to subcontractors. Notwithstanding any contrary agreement, a contractor shall pay to its subcontractors or material suppliers and each subcontractor shall in turn pay to its subcontractors or material suppliers, within 7 d

Free access — add to your briefcase to read the full text and ask questions with AI

Maine § 10 §1116 (Retainage) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

PL 1993, c. 461, §1 (NEW).

Nearby Sections

15
View on official source ↗