Text

(a)(1) A unit may assert a contract claim against a contractor by sending written notice to the contractor and the procurement officer that states:
(i)the basis for the contract claim;
(ii)to the extent known, the amount, or the performance or other action, requested by the unit in the contract claim; and
(iii)the date by which the contractor is required to provide a written response to the contract claim.
(2)On receipt of a contract claim from a unit, a procurement officer:
(i)shall review the substance of the contract claim;
(ii)may request additional information or substantiation through an appropriate procedure; and
(iii)may discuss or, if appropriate, negotiate the

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
§ 15-101
§ 15-101
§ 15-102
§ 15-102
§ 15-103
§ 15-103
§ 15-104
§ 15-104
§ 15-105
§ 15-105
§ 15-106
§ 15-106
§ 15-107
§ 15-107
§ 15-108
§ 15-108
§ 15-109
§ 15-109
§ 15-110
§ 15-110
§ 15-111
§ 15-111
§ 15-112
§ 15-112
§ 15-113
§ 15-113
§ 15-201
§ 15-201
§ 15-202
§ 15-202
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maryland § 15-219.1, Counsel Stack Legal Research, https://law.counselstack.com/statute/md/gsf/15-219.1.