Text

(a)Except to the extent a shorter period is prescribed by regulation governing differing site conditions, a contractor shall file a written notice of a claim relating to a procurement contract for construction within 30 days after the basis for the claim is known or should have been known.
(b)Unless extended by the unit, within 90 days after submitting a notice of a contract claim under a procurement contract for construction, a contractor shall submit to the unit a written explanation that states:
(1)the amount of the contract claim;
(2)the facts on which the contract claim is based; and
(3)all relevant data and correspondence that may substantiate the contract claim.
(c)(1) Subject to paragraph (2) of this subsection, the he

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
§ 15-101
§ 15-101
§ 15-102
§ 15-102
§ 15-103
§ 15-103
§ 15-104
§ 15-104
§ 15-105
§ 15-105
§ 15-106
§ 15-106
§ 15-107
§ 15-107
§ 15-108
§ 15-108
§ 15-109
§ 15-109
§ 15-110
§ 15-110
§ 15-111
§ 15-111
§ 15-112
§ 15-112
§ 15-113
§ 15-113
§ 15-201
§ 15-201
§ 15-202
§ 15-202
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maryland § 15-219, Counsel Stack Legal Research, https://law.counselstack.com/statute/md/gsf/15-219.