Maryland Statutes

§ 7-210

Maryland·Article gpu Public Utilities·Title 7
(a)This section does not apply to Baltimore City.
(b)(1) A municipal corporation may not build, maintain, or operate a plant for supplying gas or electricity for other than municipal purposes unless the municipal corporation has a certificate of authority from the Commission.
(2)If the Commission denies the certificate of authority, the municipal corporation may not reapply for a certificate until at least 6 months have elapsed from the date that the Commission denied the previous application.
(c)Subject to subsection (b) of this section, a municipal corporation in the business of supplying electricity for other than municipal purposes may own or finance an interest in an electric plant to secure an entitlement of electricity for its customers. (d

Free access — add to your briefcase to read the full text and ask questions with AI

Maryland § 7-210 — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
§ 7-1001
§ 7-1001
§ 7-1002
§ 7-1002
§ 7-1003
§ 7-1003
§ 7-1004
§ 7-1004
§ 7-1005
§ 7-1005
§ 7-1006
§ 7-1006
§ 7-1007
§ 7-1007
§ 7-101
§ 7-101
§ 7-102
§ 7-102
§ 7-103
§ 7-103
§ 7-104
§ 7-104
§ 7-105
§ 7-105
§ 7-106
§ 7-106
§ 7-107
§ 7-107
§ 7-108
§ 7-108
View on official source ↗