Text

(a)The Commission shall include specifications in a procurement solicitation issued under § 7–1224 of this subtitle that require each proposal to:
(1)include a proposed pricing schedule for the transmission energy storage project that:
(i)is for at least 15 years; and
(ii)represents the anticipated monthly wholesale value of capacity per megawatt and other benefits identified in a cost–benefit analysis, but not including any anticipated wholesale energy and ancillary services revenue;
(2)include a cost–benefit analysis of the project and proposed pricing schedule comparison on a dollar–per–megawatt–hour basis, including an analysis of:
(i)the locational value and time to deployment of the energy storage device

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
§ 7-1001
§ 7-1001
§ 7-1002
§ 7-1002
§ 7-1003
§ 7-1003
§ 7-1004
§ 7-1004
§ 7-1005
§ 7-1005
§ 7-1006
§ 7-1006
§ 7-1007
§ 7-1007
§ 7-101
§ 7-101
§ 7-102
§ 7-102
§ 7-103
§ 7-103
§ 7-104
§ 7-104
§ 7-105
§ 7-105
§ 7-106
§ 7-106
§ 7-107
§ 7-107
§ 7-108
§ 7-108
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maryland § 7-1225, Counsel Stack Legal Research, https://law.counselstack.com/statute/md/gpu/7-1225.