Maryland Statutes

§ 5-305

Maryland § 5-305
JurisdictionMaryland
Article gpuPublic Utilities
Title5

This text of Maryland § 5-305 is published on Counsel Stack Legal Research, covering Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Md. Code Ann., Public Utilities § 5-305 (2026).

Text

(a)This section applies to a project by an investor–owned gas company, electric company, or combination gas and electric company involving the construction, reconstruction, installation, demolition, restoration, or alteration of any underground gas or electric infrastructure of the company, and any related traffic control activities.
(b)An investor–owned gas company, electric company, or combination gas and electric company shall require a contractor or subcontractor on a project described in subsection (a) of this section to pay its employees not less than the prevailing wage rate determined solely by the Commissioner of Labor and Industry in a process substantially similar to the process established under Title 17, Subtitle 2 of the State Finance and Procurement Article.

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
§ 5-101
§ 5-101
§ 5-102
§ 5-102
§ 5-103
§ 5-103
§ 5-104
§ 5-104
§ 5-105
§ 5-105
§ 5-106
§ 5-106
§ 5-201
§ 5-201
§ 5-202
§ 5-202
§ 5-203
§ 5-203
§ 5-204
§ 5-204
§ 5-205
§ 5-205
§ 5-301
§ 5-301
§ 5-302
§ 5-302
§ 5-303
§ 5-303
§ 5-304
§ 5-304
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maryland § 5-305, Counsel Stack Legal Research, https://law.counselstack.com/statute/md/gpu/5-305.