Maryland Statutes

§ 15-823

Maryland § 15-823
JurisdictionMaryland
Article genEnvironment
Title15

This text of Maryland § 15-823 is published on Counsel Stack Legal Research, covering Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Md. Code Ann., Environment § 15-823 (2026).

Text

(a)After receiving notification from the Department that the application for a permit has been approved, but prior to commencing mining, the applicant shall file with the Department a bond for each mining operation, on a form to be prescribed and furnished by the Department, payable to the State and conditioned that the operator will perform faithfully all the requirements of this subtitle.
(b)The amount of the bond required shall be for a maximum of $1,250 per acre based on the number of acres of affected land covered by the permit. But, a bond may not be filed for less than $8,000. However, the Department shall determine whether the total bond fee is unreasonable and excessive for a particular tract of land and whether a lesser total amount for the bond is sufficient to cove

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
§ 15-1001
§ 15-1001
§ 15-101
§ 15-101
§ 15-1101
§ 15-1101
§ 15-1102
§ 15-1102
§ 15-1103
§ 15-1103
§ 15-1104
§ 15-1104
§ 15-1105
§ 15-1105
§ 15-1106
§ 15-1106
§ 15-1107
§ 15-1107
§ 15-1108
§ 15-1108
§ 15-1109
§ 15-1109
§ 15-1201
§ 15-1201
§ 15-1202
§ 15-1202
§ 15-1203
§ 15-1203
§ 15-1204
§ 15-1204
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Maryland § 15-823, Counsel Stack Legal Research, https://law.counselstack.com/statute/md/gen/15-823.