(a)The Department shall approve and grant or deny the permit requested as expeditiously as possible, but not later than 30 days after the application forms or any supplemental information required are filed with the Department. The Department shall process the permit application concurrently with any local or county land use and zoning reviews.
(b)The Department may deny the permit on finding that:
(1)Any requirement of this subtitle or any rule or regulation adopted under it will be violated by the proposed operation;
(2)The operation will have an unduly adverse effect on wildlife or fresh water, estuarine, or marine fisheries;
(3)The applicant has failed to provide applicable permits or approvals covering the operation from all State an

Free access — add to your briefcase to read the full text and ask questions with AI

Maryland § 15-810 — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
§ 15-1001
§ 15-1001
§ 15-101
§ 15-101
§ 15-1101
§ 15-1101
§ 15-1102
§ 15-1102
§ 15-1103
§ 15-1103
§ 15-1104
§ 15-1104
§ 15-1105
§ 15-1105
§ 15-1106
§ 15-1106
§ 15-1107
§ 15-1107
§ 15-1108
§ 15-1108
§ 15-1109
§ 15-1109
§ 15-1201
§ 15-1201
§ 15-1202
§ 15-1202
§ 15-1203
§ 15-1203
§ 15-1204
§ 15-1204
View on official source ↗