§ 2 — Time period for completion of permit review and issuance of final decision

Massachusetts § 2
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title VIICITIES, TOWNS AND DISTRICTS
Ch. 43EEXPEDITED STATE PERMITTING

This text of Massachusetts § 2 (Time period for completion of permit review and issuance of final decision) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 43E, § 2 (2026).

Text

Section 2.

(a)Issuing authorities shall complete permit reviews and final decisions within 180 days, or 210 days for permit processes requiring a public comment period, subject to an extension under section 5, for projects that are in:
(i)priority development sites designated under chapter 43D;
(ii)located within a growth district;
(iii)provided the applicant has received a certificate indicating the completion of the process under sections 61 to 62H, inclusive, of chapter 30; and (iv) provided neither the project nor any portion of the project shall be in a wetland as defined by section 40 of chapter 131, tidelands as defined by section 1 of chapter 91, priority habitat as delineated by the division of fisheries and wildlife under chapter 131A or an area of critical environmental conc

Free access — add to your briefcase to read the full text and ask questions with AI

View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 2, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/43E/2.