Massachusetts Statutes
§ 2 — Time period for completion of permit review and issuance of final decision
Massachusetts·Part I ADMINISTRATION OF THE GOVERNMENT·Title VII CITIES, TOWNS AND DISTRICTS·Ch. 43E EXPEDITED STATE PERMITTING
Section 2.
(a)Issuing authorities shall complete permit reviews and final decisions within 180 days, or 210 days for permit processes requiring a public comment period, subject to an extension under section 5, for projects that are in:
(i)priority development sites designated under chapter 43D;
(ii)located within a growth district;
(iii)provided the applicant has received a certificate indicating the completion of the process under sections 61 to 62H, inclusive, of chapter 30; and (iv) provided neither the project nor any portion of the project shall be in a wetland as defined by section 40 of chapter 131, tidelands as defined by section 1 of chapter 91, priority habitat as delineated by the division of fisheries and wildlife under chapter 131A or an area of critical environmental conc
Free access — add to your briefcase to read the full text and ask questions with AI
Massachusetts § 2 (Time period for completion of permit review and issuance of final decision) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.