§ 7 — Cost-plus not to exceed guaranteed maximum price form of contract

Massachusetts § 7
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title XXILABOR AND INDUSTRIES
Ch. 149APUBLIC CONSTRUCTION ALTERNATIVE DELIVERY METHODS

This text of Massachusetts § 7 (Cost-plus not to exceed guaranteed maximum price form of contract) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 149A, § 7 (2026).

Text

Section 7.

(a)Each contract for a building project procured pursuant to sections 1 to 9, inclusive, shall utilize a cost-plus not to exceed guaranteed maximum price form of contract in which the public agency shall be entitled to monitor and audit all project costs. The construction management at risk firm shall not be entitled to share in any savings between the final guaranteed maximum price figure and the final cost of the work including the fee of the construction management at risk firm, except that the public agency may include an incentive clause with the contract for various performance objectives; but, the incentive clause shall not include an incentive that exceeds 1 per cent of the estimated construction cost.
(b)In establishing the schedule and process for determining a guaran

Free access — add to your briefcase to read the full text and ask questions with AI

View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 7, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/149A/7.