§ 4 — Detailed application; notice to proceed; exempt agencies

Massachusetts § 4
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title XXILABOR AND INDUSTRIES
Ch. 149APUBLIC CONSTRUCTION ALTERNATIVE DELIVERY METHODS

This text of Massachusetts § 4 (Detailed application; notice to proceed; exempt agencies) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 149A, § 4 (2026).

Text

Section 4.

(a)Before undertaking a building project using construction management at-risk services, a public agency shall notify and submit a detailed application to proceed to the office of the inspector general. The detailed application shall conform to regulations and procedures promulgated by the inspector general. In order to receive a notice to proceed from the office of the inspector general, the public agency shall demonstrate the following:—
(1)The public agency has authorization from its governing body to enter into a contract with a construction management at risk firm. The authorization shall include the results of any public vote if applicable.
(2)The public agency has the capacity, a plan and procedures in place and approved of by the governing body, where appropriate, to ef

Free access — add to your briefcase to read the full text and ask questions with AI

View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 4, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/149A/4.