§ 3 — Owner's project manager; designer

Massachusetts § 3
JurisdictionMassachusetts
Part IADMINISTRATION OF THE GOVERNMENT
Title XXILABOR AND INDUSTRIES
Ch. 149APUBLIC CONSTRUCTION ALTERNATIVE DELIVERY METHODS

This text of Massachusetts § 3 (Owner's project manager; designer) is published on Counsel Stack Legal Research, covering Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mass. Gen. Laws ch. 149A, § 3 (2026).

Text

Section 3.

(a)Before procuring the services of a designer pursuant to subsection (b) and prior to submitting an application to use the construction management at risk delivery method pursuant to section 4, the public agency shall procure or otherwise employ the services of an owner's project manager pursuant to section 44A1/2 of chapter 149. The owner's project manager may assist the public agency in the procurement of the designer.
(b)Before submitting an application to use the construction management at risk delivery method pursuant to section 4, the public agency shall procure the services of a designer for the building project. In procuring the services of a designer, the public agency shall do so in a manner consistent with sections 38A1/2 to 39O, inclusive, of chapter 7. The designe

Free access — add to your briefcase to read the full text and ask questions with AI

View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Massachusetts § 3, Counsel Stack Legal Research, https://law.counselstack.com/statute/ma/149A/3.