§ 48:255 — Award of contract; time limitations and exceptions; bond of successful bidder;

Louisiana § 48:255
JurisdictionLouisiana
Title 48Roads, Bridges and Ferries

This text of Louisiana § 48:255 (Award of contract; time limitations and exceptions; bond of successful bidder;) is published on Counsel Stack Legal Research, covering Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
La. Stat. Ann. § 48:255 (2026).

Text

§255. Award of contract; time limitations and exceptions; bond of successful bidder; rejection of certain bidders A. The department shall establish specific bidding requirements, in accordance with the provisions of this Part, provisions of the Federal Highway Administration, if applicable, and other provisions as necessary and will include these requirements in the project specifications and bid package issued to prospective bidders. Bids of prospective bidders shall conform to these requirements. Bids not submitted in accordance with this Subpart or such other specified requirements are irregular and must be rejected by the department. B.

(1)For all construction, maintenance, or improvement projects for department facilities or other public facility projects, advertised and let by the de

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Legislative History

Acts 1990, No. 206, §1, eff. July 1, 1990; Acts 1997, No. 1112, §1, eff. July 14, 1997; Acts 1999, No. 652, §1; Acts 1999, No. 1284, §3; Acts 2001, No. 575, §1; Acts 2006, No. 14, §1, eff. May 4, 2006; Acts 2006, No. 324, §1, eff. June 13, 2006; Acts 2007, No. 386, §§1, 2, eff. July 1, 2007; Acts 2025, No. 380, §1.