A.The facility planning and control section shall be responsible for directing final payment for work done on each project. However, if upon final inspection of any project it shall be found that the plans, specifications, contract, or change orders for the project shall not have been fully complied with, the facility planning and control section shall, until such compliance shall have been effected or adjustments satisfactory to it shall have been made, refuse to direct such payment.
B.Upon completion of the project the facility planning and control section shall release it to the agency. The facility planning and control section shall be responsible for making an inspection of the project prior to the expiration of the guarantee period to observe any defects which may appear within one

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Acts 1989, No. 836, §1, eff. July 1, 1989.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Louisiana § 39:125, Counsel Stack Legal Research, https://law.counselstack.com/statute/la/39%3A125.