§ 39:122 — Commencement of work; delays in construction; public statement; allocated funds

Louisiana § 39:122
JurisdictionLouisiana
Title 39Procurement and Contract

This text of Louisiana § 39:122 (Commencement of work; delays in construction; public statement; allocated funds) is published on Counsel Stack Legal Research, covering Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
La. Stat. Ann. § 39:122 (2026).

Text

§122. Commencement of work; delays in construction; public statement; allocated funds A.

(1)No work shall commence and no contract shall be entered into for any project contained in the Capital Outlay Act unless and until funds are available from the cash sources indicated in the act or from the sale of bonds or from a line of credit approved by the State Bond Commission, except for funds that are received as supplemental funds for ongoing projects for which contracts have been issued and contracts for Department of Transportation and Development projects which are subject to the provisions of R.S. 48:251(D).
(2)State-owned projects planned for the fiscal year in which an appropriation has been funded shall be commenced in that fiscal year and the administering agencies shall diligently c

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Acts 1989, No. 836, §1, eff. July 1, 1989; Acts 1997, No. 1346, §1, eff. July 1, 1997; Acts 1998, 1st Ex. Sess., No. 161, §2, eff. May 7, 1998; Acts 2008, No. 911, §1, eff. July 1, 2008; Acts 2020, 2 nd Ex. Sess., No. 39, §1, eff. Oct. 28, 2020; Acts 2023, No. 388, §1.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Louisiana § 39:122, Counsel Stack Legal Research, https://law.counselstack.com/statute/la/39%3A122.