Kansas Statutes

§ 76-7,132 — Same; construction management at-risk project delivery procedures; construction manager, selection of; construction services bid, notice requirements

Kansas § 76-7,132
JurisdictionKansas
Ch. 76STATE INSTITUTIONS AND AGENCIES; HISTORICAL PROPERTY
Art. 7STATE EDUCATIONAL INSTITUTIONS; MANAGEMENT AND OPERATION

This text of Kansas § 76-7,132 (Same; construction management at-risk project delivery procedures; construction manager, selection of; construction services bid, notice requirements) is published on Counsel Stack Legal Research, covering Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kan. Stat. Ann. § 76-7,132 (2026).

Text

Construction management at-risk project delivery procedures shall be conducted as follows:

(a)The state board shall determine the scope and level of detail required to permit qualified construction manager or general contractors to submit construction management at-risk proposals in accordance with the request for proposals given the nature of the project.
(b)Prior to completion of the construction documents, but as early as during the schematic design phase, the construction manager or general contractor shall be selected. The project design professional may be employed or retained by the institution to assist in the selection process.
(c)The institution shall publish a notice of the request for qualifications and proposals for the required project services at least 15 days prior to th

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 75-430a
Kansas § 75-430a
§ 60-1111
Kansas § 60-1111

Legislative History

L. 2009, ch. 86, § 7; L. 2015, ch. 11, § 6; July 1.

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Kansas § 76-7,132, Counsel Stack Legal Research, https://law.counselstack.com/statute/ks/76-7%2C132.