§ 75-37,144 — Same; construction management at-risk project delivery procedures

Kansas § 75-37,144
JurisdictionKansas
Ch. 75STATE DEPARTMENTS; PUBLIC OFFICERS AND EMPLOYEES
Art. 37DEPARTMENT OF ADMINISTRATION

This text of Kansas § 75-37,144 (Same; construction management at-risk project delivery procedures) is published on Counsel Stack Legal Research, covering Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kan. Stat. Ann. § 75-37,144 (2026).

Text

Construction management at-risk project delivery procedures shall be conducted as follows:

(a)The director shall determine the scope and level of detail required to permit qualified construction manager or general contractors to submit construction management at-risk proposals in accordance with the request for proposals given the nature of the project.
(b)Prior to completion of the construction documents, but as early as during the schematic design phase, the construction manager or general contractor shall be selected. The project design professional may be employed or retained by the agency to assist in the selection process. The design professional shall be selected and its contract negotiated in compliance with K.S.A. 75-1257 and 75-5804, and amendments thereto.
(c)The agency shall

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 75-1257
Kansas § 75-1257
§ 75-430a
Kansas § 75-430a
§ 60-1111
Kansas § 60-1111
§ 75-1250
Kansas § 75-1250
§ 75-3783
Kansas § 75-3783

Legislative History

L. 2006, ch. 80, § 4; L. 2015, ch. 11, § 3; July 1.

Nearby Sections

15
§ 75-101
Oath
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Kansas § 75-37,144, Counsel Stack Legal Research, https://law.counselstack.com/statute/ks/75-37%2C144.