Construction management at-risk project delivery procedures shall be conducted as follows:

(a)The board shall determine the scope and level of detail required to permit a qualified firm to submit construction management at-risk proposals in accordance with the request for proposals given the nature of the project.
(b)Prior to completion of the construction documents, or as early as during the initiation of the project, the construction manager or general contractor shall be selected. The project design professional may be employed or retained by the board to assist in the selection process.
(c)The board shall publish a notice of the request for qualifications and proposals for the required project services at least 15 days prior to the commencement of such requests in the official newsp

Free access — add to your briefcase to read the full text and ask questions with AI

Related

§ 64-101
Kansas § 64-101
§ 60-1111
Kansas § 60-1111

Legislative History

L. 2008, ch. 148, § 12; L. 2010, ch. 57, § 7; L. 2015, ch. 11, § 1; July 1.