§ 5-32-4-7 — Public agency options if CMc contract terminated or not executed
Indiana § 5-32-4-7
JurisdictionIndiana
Title 5STATE AND LOCAL ADMINISTRATION
Art. 32EMPLOYMENT OF CONSTRUCTION
Ch. 4CMc Contract
This text of Indiana § 5-32-4-7 (Public agency options if CMc contract terminated or not executed) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Ind. Code § 5-32-4-7 (2026).
Text
(a)If any of the following occur, the public
agency may proceed as described in subsection (b):
(1)The CMc contract is terminated under section 6 of this
chapter.
(2)The public agency and the selected offeror are unable to reach
agreement on a CMc contract.
(3)The selected offeror does not provide the required bonds as
provided in the RFP or this article.
(b)If any of the events described in subsection (a)(1), (a)(2), or
(a)(3) occur, the public agency may do any of the following:
(1)Negotiate a contract with another offeror.
(2)Award contracts and complete the project under any other
applicable public works statute.
(3)Terminate the project.
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
As added by P.L.128-2014, SEC.1.
Nearby Sections
15
§ 5-1-1-1
Validation§ 5-1-1-2
Repealed§ 5-1-10-1
Issuance; purpose; restrictions§ 5-1-11-7
Restrictions on powers§ 5-1-11.5-1
"ADM"§ 5-1-11.5-2
"Bonds"§ 5-1-11.5-3
Application to certain school corporations§ 5-1-12-1
"Municipal corporation" definedCite This Page — Counsel Stack
Bluebook (online)
Indiana § 5-32-4-7, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/5-32-4-7.