§ 5-16-5.5-3.5 — Retainage; options to determine amount

Indiana § 5-16-5.5-3.5
JurisdictionIndiana
Title 5STATE AND LOCAL ADMINISTRATION
Art. 16PUBLIC WORKS
Ch. 5.5Retainage, Bonds, and Payment of Contractors and

This text of Indiana § 5-16-5.5-3.5 (Retainage; options to determine amount) is published on Counsel Stack Legal Research, covering Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ind. Code § 5-16-5.5-3.5 (2026).

Text

5.

(a)To determine the amount of retainage to be withheld, a state agency shall elect one (1) of the following options:
(1)Withhold no more than six percent (6%) of the dollar value of all work satisfactorily completed until the public work is fifty percent (50%) complete, and nothing further after that.
(2)Withhold no more than three percent (3%) of the dollar value of all work satisfactorily completed until the public work is substantially complete.
(b)If upon substantial completion of the work there are any remaining uncompleted minor items, an amount computed under section 6 of this chapter shall be withheld until those items are completed. As added by Acts 1980, P.L.33, SEC.1. Amended by P.L.133-2007, SEC.7; P.L.28-2025, SEC.1.

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Indiana § 5-16-5.5-3.5, Counsel Stack Legal Research, https://law.counselstack.com/statute/in/5-16-5.5-3.5.