Indiana Statutes

§ 5-16-5-1 — Withholding final payments; filing claims for payment; release of surety

Indiana·Title 5 STATE AND LOCAL ADMINISTRATION·Art. 16 PUBLIC WORKS·Ch. 5 Withholding and Bond to Secure Payment of
(a)Except as otherwise provided in this chapter, when a public work is performed under contract at the expense of the state or a commission created by law, the public body shall withhold final payment to the contractor until the contractor has paid to:
(1)all subcontractors;
(2)all suppliers of materials for material furnished;
(3)all labor employed in the public work; and
(4)all those furnishing any service in relation to or in connection with the public work; all bills due and owing to the persons described in subdivisions (1) through (4) who have filed a claim under subsection (c).
(b)If there is not a sufficient sum owing to the contractor on the contract to pay all the bills, then the sum owing on the contract shall be prorated in payment of all the bills among the persons entit

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 5-16-5-1 (Withholding final payments; filing claims for payment; release of surety) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Evansville v. Verplank Concrete & Supply, Inc.
400 N.E.2d 812 (Indiana Court of Appeals, 1980)
17 case citations

Nearby Sections

15
View on official source ↗