§ 10-18-4-8 — Changes to designs, plans, and specifications

Indiana·Title 10 PUBLIC SAFETY·Art. 18 WAR MEMORIALS·Ch. 4 City War Memorials
(a)Subject to subsections (b) and (c), any changes made in the designs, plans, and specifications in the progress of the work:
(1)must be agreed upon in advance between the board of public works and the contractor and architect; and
(2)must have the cost of the changes fixed by contract in writing. If changes made do not comply with subdivisions (1) and (2), the person making the changes is not entitled to any compensation for the changes.
(b)A change may not be made that will increase the total cost of the World War memorial as prescribed in this chapter.
(c)Any changes do not affect the obligation of or release any surety on any contract or bond executed or given in connection with the building of the World War memorial structures, but the liability of the surety is extended so as t

Free access — add to your briefcase to read the full text and ask questions with AI

Indiana § 10-18-4-8 (Changes to designs, plans, and specifications) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

As added by P.L.2-2003, SEC.9.