§ 10-18-2-7 — Changes to design or plan
All changes made in the designs or plans for a world war memorial are subject to the following:
(1)Changes must be agreed upon in writing, in advance, between
the county executive and the contractor and architect.
(2)Compensation may not be paid for design or plan changes.
(3)Changes may not be made that will increase the total cost of
the world war memorial.
(4)Changes may not affect the obligation of or release any surety
or bondsmen on any contract or bond executed or given in
connection with the building of the world war memorial.
However, the liability shall be extended to embrace and cover the
changes.
[Pre-2003 Recodification Citation: 10-7-1-7.]
Free access — add to your briefcase to read the full text and ask questions with AI
Indiana § 10-18-2-7 (Changes to design or plan) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
As added by P.L.2-2003, SEC.9.
Nearby Sections
15
§ 10-10-1-1
"Prior law"§ 10-10-1-2
Purpose of recodification§ 10-10-1-3
Statutory construction of recodification§ 10-10-1-4
Effect of recodification§ 10-10-1-5
Recodification of prior law§ 10-10-1-6
References to repealed statutes§ 10-10-1-7
References to citations§ 10-10-1-8
References to prior rules§ 10-10-1-9
References to prior law§ 10-10.5-1-1
Applicability of definitions§ 10-10.5-1-2
"Indiana first responder"§ 10-10.5-1-3
"Law enforcement officer"§ 10-10.5-1-4
"PSAP"§ 10-10.5-1-5
"Public safety agency"§ 10-10.5-1-6
"Public safety telecommunicator"