Written notice by subcontractor; service; when notice not necessary; form of notice.

(a)Subcontractors, or parties furnishing labor, materials, fixtures, apparatus, machinery, or services, may at any time after making his or her contract with the contractor, and shall within 90 days after the completion thereof, or, if extra or additional work or material is delivered thereafter, within 90 days after the date of completion of such extra or additional work or final delivery of such extra or additional material, cause a written notice of his or her claim and the amount due or to become due thereunder, to be provided to the owner of record or the owner of record's agent or architect, or the superintendent having charge of the building or improvement and to the lending agency, if known, with

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

(Source: P.A. 103-827, eff. 1-1-25 .)