This text of Idaho § 61-1709 (COMMISSION PROCEDURES — ADMINISTRATIVE REMEDY — RECONSIDERATION — JUDICIAL REVIEW) is published on Counsel Stack Legal Research, covering Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Idaho Code § 61-1709 (2026).

Text

(1)All matters arising under this chapter shall be governed by the commission’s rules of procedure.
(2)The commission’s proceeding to review an application for a route certificate for the construction of transmission facilities in a designated national interest electric transmission corridor shall constitute a necessary administrative remedy for a person aggrieved by a local government’s final land use action on a transmitting utility’s application to construct transmission facilities in a designated national interest electric transmission corridor. Judicial review shall not be available from a local government’s final land use decision concerning a transmitting utility’s application to construct transmission facilities in a national interest electric transmission corridor. A person aggr

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

[61-1709, added 2007, ch. 186, sec. 1, p. 543.]