§ 39-4117 — PROCESSING BUILDING PERMITS — TIMELY REVIEW
Idaho § 39-4117
This text of Idaho § 39-4117 (PROCESSING BUILDING PERMITS — TIMELY REVIEW) is published on Counsel Stack Legal Research, covering Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Idaho Code § 39-4117 (2026).
Text
(1)A local government that requires building permits shall make available a document that describes in detail the requirements of its building permit process. The local government shall provide the document to the public on its website and in physical form upon request.
(2)An applicant for a building permit shall make a good faith effort to submit a complete application containing the necessary documentation required by a local government as specified in the document required pursuant to subsection (1) of this section. If an application is deemed incomplete, the local government shall, within ten (10) business days of receipt of a residential building permit application and within twenty (20) business days of receipt of a commercial building permit application, provide written notice to
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
[39-4117, added 2025, ch. 272, sec. 1, p. 1164.]
Nearby Sections
15
§ 39-1003
STANDARD SEROLOGICAL TEST DEFINED§ 39-1004
LABORATORY REPORT OF TEST§ 39-1006
PENALTY FOR VIOLATIONS§ 39-101
SHORT TITLE§ 39-103
DEFINITIONSCite This Page — Counsel Stack
Bluebook (online)
Idaho § 39-4117, Counsel Stack Legal Research, https://law.counselstack.com/statute/id/39-4117.