Fla. Stat. § 403.9421 (2026).

Text

The department shall charge the applicant the following fees, as appropriate, which shall be paid into the Florida Permit Fee Trust Fund:

(1)An application fee of $240,000, plus $500 per mile for each mile of natural gas transmission pipeline corridor proposed to be located in an existing electrical transmission line right-of-way or in existing rights-of-way for roads, highways, railroads, gas, water, oil, sewer, or any other public purpose, and $1,000 per mile for each mile of natural gas transmission pipeline proposed to be located outside existing rights-of-way, not to exceed a total fee of $890,000.
(2)A postcertification fee determined as follows:
(a)For pipelines of 50 miles or less in total length, the fee shall be $75,000.
(b)For pipelines of between 50 and 150 miles in total

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

s. 1, ch. 92-284; s. 70, ch. 96-321; s. 15, ch. 2006-79.