§ 287.0585 — Late payments by contractors to subcontractors and suppliers; penalty
Florida § 287.0585
This text of Florida § 287.0585 (Late payments by contractors to subcontractors and suppliers; penalty) is published on Counsel Stack Legal Research, covering Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Fla. Stat. § 287.0585 (2026).
Text
(1)When a contractor receives from a state agency any payment for contractual services, commodities, supplies, or construction contracts, except those construction contracts subject to the provisions of chapter 339, the contractor shall pay such moneys received to each subcontractor and supplier in proportion to the percentage of work completed by each subcontractor and supplier at the time of receipt of the payment. If the contractor receives less than full payment, then the contractor shall be required to disburse only the funds received on a pro rata basis with the contractor, subcontractors, and suppliers, each receiving a prorated portion based on the amount due on the payment. If the contractor without reasonable cause fails to make payments required by this section to subcontractor
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
s. 5, ch. 85-104; s. 2, ch. 89-200; s. 9, ch. 91-162; s. 14, ch. 2005-230.
Nearby Sections
15
§ 287.001
Legislative intent§ 287.012
Definitions§ 287.022
Purchase of insurance§ 287.025
Prohibition against certain insurance coverage on specified state property or insurable subjects§ 287.032
Purpose of department§ 287.042
Powers, duties, and functions§ 287.0572
Present-value methodology§ 287.0575
Coordination of contracted servicesCite This Page — Counsel Stack
Bluebook (online)
Florida § 287.0585, Counsel Stack Legal Research, https://law.counselstack.com/statute/fl/287.0585.