Delaware Statutes
§ 6963 — Emergency procedures and contract change orders
Delaware·Title 29·Part Budget, Fiscal, Procurement and Contracting Regulations·Ch. 69 STATE PROCUREMENT·Subch. Public Works Contracting
(a)All of the provisions of this subchapter may be waived pursuant to § 6907 of this title.
(b)The awarding agency may issue a change order to the public works contract setting forth any change, addition or extra work required to be undertaken by the contractor. Such changes may be necessitated by changed situations, unforeseen conditions, strikes and acts of God. Change orders shall be issued for all changes or extra work determined to be necessary and requested by the agency, but not specified in the contract or its plans and specifications. The change order shall not:
(1)Be subject to the competitive bidding requirements of this subchapter; or
(2)Invalidate the contract, provided that such change is within the scope of the contract as set forth in the standard specifications, spe
Free access — add to your briefcase to read the full text and ask questions with AI
Delaware § 6963 (Emergency procedures and contract change orders) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
70 Del. Laws, c. 601, § 9 ; 74 Del. Laws, c. 419, § 9