§ 910 — Conditional use permit for electrical substations [For application of this section, see 85 Del. Laws, c. 44, § 2]

Delaware § 910
JurisdictionDelaware
Title26
Ch. 9TELEGRAPH, TELEPHONE AND ELECTRIC UTILITY CORPORATIONS
Subch.General Provisions

This text of Delaware § 910 (Conditional use permit for electrical substations [For application of this section, see 85 Del. Laws, c. 44, § 2]) is published on Counsel Stack Legal Research, covering Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Del. Code tit. 26, § 910 (2026).

Text

No county shall deny a conditional use permit to any electrical substation, along with any directly related project infrastructure, proposed to be located on unincorporated land within such county where the following conditions apply:

(1)The substation is being proposed to support the operation of a proposed renewable energy generation project of 250 MW or greater;
(2)The proposed substation would be located in a heavy industrial zone;
(3)An electrical substation is an allowed conditional use within the proposed zone; and
(4)The specific zoning district in which the proposed substation would be located already has an electric substation located in such zone with a rating of 230kv or greater as of August 3, 2023.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

85 Del. Laws, c. 44, § 1