Delaware Statutes
§ 2723 — Rights of owner where lien or judgment is obtained by a subcontractor
Delaware § 2723
JurisdictionDelaware
Title25
PartMortgages and Other Liens
Ch. 27Mechanics’ Liens
Subch.Enforcement in Superior Court
This text of Delaware § 2723 (Rights of owner where lien or judgment is obtained by a subcontractor) is published on Counsel Stack Legal Research, covering Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Del. Code tit. 25, § 2723 (2026).
Text
The owner of any structure built, repaired or altered by any contractor who has contracted to build, erect, alter or repair the same and furnish the materials therefor may, in case any liens are entered under this chapter upon the structure, upon any claim for materials which by the terms of the contract the contractor was bound to furnish, by any person or persons other than such contractor, retain and withhold from such contractor so much of the moneys to be paid to such contractor in pursuance of the contract made with such contractor as may be necessary to liquidate and discharge such liens; and, in case judgment is recovered by such lien creditors, the owner may apply the moneys or such part thereof as may be necessary to satisfy the judgment to the payment and satisfaction thereof. S
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
16 Del. Laws, c. 145, § 1 ; Code 1915, §§ 2843, 2843A; 29 Del. Laws, c. 225 ; 38 Del. Laws, c. 159 ; Code 1935, § 3324; 25 Del. C. 1953, § 2723; 84 Del. Laws, c. 42, § 101
Nearby Sections
15
Cite This Page — Counsel Stack
Bluebook (online)
Delaware § 2723, Counsel Stack Legal Research, https://law.counselstack.com/statute/de/25/2723.