This text of District of Columbia § 40-303.11 (Distribution of sale proceeds.) is published on Counsel Stack Legal Research, covering District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.C. Code § 40-303.11 (2026).

Text

If one, or some only, of the persons employed under the original contractor shall have served notice on the owner, as aforesaid, before payments made by him to the original contractor, said party or parties shall be entitled to priority of satisfaction out of said proceeds to the amount of such payments; but, subject to this provision, if the proceeds of sale, after paying there out the costs of the suit, shall be insufficient to satisfy the liens of said parties employed under the original contractor the said proceeds shall be distributed ratably among them to the extent of the payments accruing to the original contractor subsequently to the service of notice on the owner by said parties, as aforesaid.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Mar. 3, 1901, 31 Stat. 1386, ch. 854, § 1249

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
District of Columbia § 40-303.11, Counsel Stack Legal Research, https://law.counselstack.com/statute/dc/40-303.11.