§ 34-2705 — Requirements of person responsible for excavation or demolition.
District of Columbia § 34-2705
This text of District of Columbia § 34-2705 (Requirements of person responsible for excavation or demolition.) is published on Counsel Stack Legal Research, covering District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
D.C. Code § 34-2705 (2026).
Text
(a)In addition to the requirements of § 34-2704 , each person responsible for an excavation or demolition operation shall:
(1)Plan the excavation or demolition to avoid damage to or minimize interference with underground facilities in and near the construction area;
(2)Maintain a clearance between an underground facility and the cutting edge or point of any mechanized equipment, taking into account the known limit of control of such cutting edge or point as may be reasonably necessary to avoid damage to such underground facility; and
(3)Provide such support for underground facilities in and near the construction area, including support during backfilling operations, as may be reasonably necessary for the protection of such facilities.
(b)If a facility is damaged, under no ci
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
Mar. 4, 1981, D.C. Law 3-129, § 6, 28 DCR 264