§ 4b-92 — (Formerly Sec. 4-137b). “Lowest responsible and qualified bidder” defined. Bid bonds, certified checks, when forfeited.
Connecticut § 4b-92
JurisdictionConnecticut
Title 4bState Real Property
Ch. 60Construction and Alterations of State Buildings
This text of Connecticut § 4b-92 ((Formerly Sec. 4-137b). “Lowest responsible and qualified bidder” defined. Bid bonds, certified checks, when forfeited.) is published on Counsel Stack Legal Research, covering Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
Conn. Gen. Stat. § 4b-92 (2026).
Text
As used in this chapter and except as otherwise provided, “lowest responsible and qualified bidder” means the bidder who is prequalified pursuant to section 4a-100, and whose bid is the lowest of those bidders possessing the skill, ability and integrity necessary to faithful performance of the work based on objective criteria considering past performance and information contained in the update statement submitted pursuant to section 4b-91. Essential information in regard to such qualifications shall be submitted with the bid in such form as the awarding authority may require by specification in the bid documents and on the bid form. Every general bid shall be accompanied by a bid bond or a certified check in an amount which shall be ten per cent of the bid, provided no such bid bond or cer
Free access — add to your briefcase to read the full text and ask questions with AI
Legislative History
(P.A. 73-528, S. 2, 12; P.A. 74-246, S. 2, 11; P.A. 79-490; P.A. 82-358, S. 8, 10; 82-447, S. 2; P.A. 99-75, S. 9; P.A. 03-215, S. 2; P.A. 07-202, S. 8; P.A. 14-122, S. 68; P.A. 21-198, S. 4.) History: P.A. 74-246 deleted provision that bidder certify labor to be employed can work harmoniously with others, required objective criteria for judging bidders' qualifications and raised bid bond from 5% to 10% of bid; P.A. 79-490 exempted sub-bidders bidding less than $10,000 in labor and materials costs from bid bond requirement; P.A. 82-358 provided that bid bond or certified check is not required for general bids with estimated cost of labor and materials of less than $10,000 and raised estimated cost relative to sub-bids from $10,000 to $20,000; P.A. 82-447 amended section to eliminate all reference to sub-bidding process and to specify factors for evaluation in considering a contractor's past performance; Sec. 4-137b transferred to Sec. 4b-92 in 1989; P.A. 99-75 substituted $50,000 for $10,000; P.A. 03-215 redefined “lowest responsible and qualified bidder” and substituted “nature and scope” for “size” re projects, effective October 1, 2004; P.A. 07-202 made a technical change, effective July 10, 2007; P.A. 14-122 made technical changes; P.A. 21-198 replaced “update bid statement” with “update statement”, effective July 1, 2021. Annotation to former section 4-137b: Cited. 191 C. 497.
Nearby Sections
15
Cite This Page — Counsel Stack
Bluebook (online)
Connecticut § 4b-92, Counsel Stack Legal Research, https://law.counselstack.com/statute/ct/4b-92.