§ 38-5-103 — Power of companies to contract

Colorado § 38-5-103
JurisdictionColorado
Title 38Property -
Art.Rights-of-way: Transmission Companies

This text of Colorado § 38-5-103 (Power of companies to contract) is published on Counsel Stack Legal Research, covering Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Colo. Rev. Stat. § 38-5-103 (2026).

Text

(1)Such electric light power, gas, or pipeline company, or such city, town, or other local government shall have power to contract with any person or corporation, the owner of any lands or any franchise, easement, or interest therein over or under which the line of electric light wire power or pipeline is proposed to be laid or created for the right-of-way for the construction, maintenance, and operation of its electric light wires, pipes, poles, regulator stations, substations, or other property and for the erection, maintenance, occupation, and operation of offices at suitable distances for the public accommodation.
(2)An electric utility, as defined in section 40-15-601 (6), exercising its rights under subsection (1) of this section may, in accordance with part 6 of article

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Source: L. 07: p. 386, � 3. R.S. 08: � 2453. C.L. � 6354. CSA: C. 61, � 44. CRS 53: � 50-5-3. L. 63: p. 480, � 3. C.R.S. 1963: � 50-5-3. L. 96: Entire section amended, p. 303, � 4, effective April 12. L. 2019: Entire section amended, (SB 19-107), ch. 424, p. 3714, � 3, effective August 2.