§ 937. — 937. (Added by Stats. 2023, Ch. 394, Sec. 1.)

California·Code PUC Public Utilities Code - PUC·Div. 1. DIVISION 1. REGULATION OF PUBLIC UTILITIES·Part 1. PART 1. PUBLIC UTILITIES ACT·Ch. 4. CHAPTER 4. Regulation of Public Utilities·Art. 14.5. ARTICLE 14.5. Powering Up Californians
(a)The commission shall ensure that each electrical corporation has sufficient and timely recovery of costs to be consistent with the findings and achieve the policies and requirements of this article, including for energization projects.
(b)If requested by the electrical corporation, the commission shall authorize, within 180 days of the request, the use of a ratemaking mechanism that does all of the following:
(1)Authorizes the electrical corporation to track costs for energization projects placed in service after January 1, 2024, that exceed the costs included in the electrical corporation’s annual authorized revenue requirement for energization, as established in the electrical corporation’s general rate case or any other proceeding.
(2)Requires the commission to establish an

Free access — add to your briefcase to read the full text and ask questions with AI

California § 937. (937. (Added by Stats. 2023, Ch. 394, Sec. 1.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Legislative History

Added by Stats. 2023, Ch. 394, Sec. 1. (SB 410) Effective January 1, 2024. Repealed as of January 1, 2027, by its own provisions.