§ 25341. — 25341. (Added by Stats. 2006, Ch. 638, Sec. 2.)

California § 25341.
JurisdictionCalifornia
Code PRCPublic Resources Code - PRC
Div. 15.DIVISION 15. ENERGY CONSERVATION AND DEVELOPMENT
Ch. 4.3.CHAPTER 4.3. Designation of Transmission Corridors

This text of California § 25341. (25341. (Added by Stats. 2006, Ch. 638, Sec. 2.)) is published on Counsel Stack Legal Research, covering California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cal. Public Resources Code - PRC Code § 25341. (2026).

Text

(a)Within a designated transmission corridor zone, within 10 days of accepting as complete an application pursuant to Section 65943 of the Government Code for a development project that a city or county determines would threaten the potential to construct a high-voltage electric transmission line, the city or county shall notify the commission of the proposed development project. The notice shall include a copy of the application, and set a deadline that is not less than 60 days from the date of the notice for the commission to provide written comments to the city or county regarding the proposed development project.
(b)If the commission finds that the proposed development project would threaten the potential to construct a high-voltage electric transmission line within the designated tr

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Added by Stats. 2006, Ch. 638, Sec. 2. Effective January 1, 2007.