(a)This section applies to a contract between a public utility and a direct contractor for all or part of a work of improvement.
(b)Unless the direct contractor and a subcontractor otherwise agree in writing, within 21 days after receipt of a progress payment from the public utility the direct contractor shall pay the subcontractor the
amount allowed the direct contractor on account of the work performed by the subcontractor to the extent of the subcontractor’s interest in the work. If there is a good faith dispute over all or part of the amount due on a progress payment from the direct contractor to a subcontractor, the direct contractor may withhold an amount not in excess of 150 percent of the disputed amount.
(c)A direct contractor that violates this section is liable to the subco
Free access — add to your briefcase to read the full text and ask questions with AI
California § 8802. (8802. (Added by Stats. 2010, Ch. 697, Sec. 20.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.