§ 8612. — 8612. (Amended (as to be added by Stats. 2010, Ch. 697) by Stats. 2011, Ch. 700, Sec. 3.)
California·Code CIV Civil Code - CIV·Div. 4. DIVISION 4. GENERAL PROVISIONS·Title 2.·Part 6. TITLE 2. PRIVATE WORKS OF IMPROVEMENT·Ch. 6. CHAPTER 6. Payment Bond
(a)In order to enforce a claim against a payment bond under this title, a claimant shall give the preliminary notice provided in Chapter 2 (commencing with Section 8200).
(b)If preliminary notice was not given as provided in Chapter 2 (commencing with Section 8200), a claimant may enforce a claim by giving written notice to the surety
and the bond principal within 15 days after recordation of a notice of completion. If no notice of completion has been recorded, the time for giving written notice to the surety and the bond principal is extended to 75 days after completion of the work of improvement.
(c)Commencing July 1, 2012, and except as provided in subdivision (b), if the preliminary notice was required to be given by a person who has no direct contractual relationship with the contr
Free access — add to your briefcase to read the full text and ask questions with AI
California § 8612. (8612. (Amended (as to be added by Stats. 2010, Ch. 697) by Stats. 2011, Ch. 700, Sec. 3.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Legislative History
Amended (as to be added by Stats. 2010, Ch. 697) by Stats. 2011, Ch. 700, Sec. 3. (SB 293) Effective January 1, 2012. Operative July 1, 2012, pursuant to Stats. 2010, Ch. 697, Sec. 105, and this section's own provisions.