§ 8414. — 8414. (Added by Stats. 2010, Ch. 697, Sec. 20.)

California § 8414.
JurisdictionCalifornia
Code CIVCivil Code - CIV
Div. 4.DIVISION 4. GENERAL PROVISIONS
Title2.
Part 6.TITLE 2. PRIVATE WORKS OF IMPROVEMENT
Ch. 4.CHAPTER 4. Mechanics Lien
Art. 2.ARTICLE 2. Conditions to Enforcing a Lien

This text of California § 8414. (8414. (Added by Stats. 2010, Ch. 697, Sec. 20.)) is published on Counsel Stack Legal Research, covering California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cal. Civil Code - CIV Code § 8414. (2026).

Text

A claimant other than a direct contractor may not enforce a lien unless the claimant records a claim of lien within the following times:

(a)After the claimant ceases to provide work.
(b)Before the earlier of the following times:
(1)Ninety days after completion of the work of improvement.
(2)Thirty days after the owner records a notice of completion or cessation.

Free access — add to your briefcase to read the full text and ask questions with AI

Legislative History

Added by Stats. 2010, Ch. 697, Sec. 20. (SB 189) Effective January 1, 2011. Operative July 1, 2012, by Sec. 105 of Ch. 697 and by Section 8052.