§ 45-1209 — Notice of completion; license of final approval; removal of dam

Arizona·Title 45 Arizona Revised Statutes·Ch. 6 DAMS AND RESERVOIRS·Art. 1 Supervision of Dams, Reservoirs and Projects
A.Immediately upon completion or enlargement of a dam, notice of completion shall be given to the director. As soon as possible thereafter supplementary drawings or descriptive matter showing or describing the dam as actually constructed shall be filed with the director which shall include:
1.A record of all grout holes and grouting.
2.A record of permanent location points and bench marks.
3.A record of tests of concrete or other material used in the construction of the dam.
4.A record of other items of permanent value bearing on safety and permanence of construction.
B.When an existing dam is enlarged, the supplementary drawings and descriptive matter need apply only to the new work.
C.The owner of a completed dam shall file an affidavit of the total cost of the dam comprised

Free access — add to your briefcase to read the full text and ask questions with AI

Arizona § 45-1209 (Notice of completion; license of final approval; removal of dam) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Nearby Sections

15
View on official source ↗