§ 41-2617 — Contracts for procurement of construction; delay; recovery of damages by contractor
Arizona·Title 41 Arizona Revised Statutes·Ch. 23 ARIZONA PROCUREMENT CODE·Art. 9 Legal and Contractual Remedies
A contract for the procurement of construction shall include a provision which provides for negotiations between the state governmental unit and the contractor for the recovery of damages related to expenses incurred by the contractor for a delay for which the state governmental unit is responsible, which is unreasonable under the circumstances and which was not within the contemplation of the parties to the contract. This section shall not be construed to void any provision in the contract which requires notice of delays, provides for arbitration or other procedure for settlement or provides for liquidated damages.
Free access — add to your briefcase to read the full text and ask questions with AI
Arizona § 41-2617 (Contracts for procurement of construction; delay; recovery of damages by contractor) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.
Related
Canon School Dist. 50 v. Wes Const.
848 P.2d 848 (Court of Appeals of Arizona, 1992)
Canon School District No. 50 v. W.E.S. Construction Co.
848 P.2d 848 (Court of Appeals of Arizona, 1992)
Nearby Sections
15
§ 41-1001
Definitions§ 41-1001.01
Regulatory bill of rights; small businesses§ 41-1003
Required rule making§ 41-1004
Waiver§ 41-1005
Exemptions§ 41-1007
Award of costs and fees against a department in administrative hearings; exceptions; definitions§ 41-1008
Fees; specific statutory authority§ 41-101.01
Authority to accept and expend certain funds§ 41-101.02
Authority to enter reciprocal aid agreements