§ 41-2577 — Progress payments; changed or additional work; attorney fees; definitions

Arizona § 41-2577
JurisdictionArizona
Title 41Arizona Revised Statutes
Ch. 23ARIZONA PROCUREMENT CODE
Art. 5Procurement of Construction and Specified Professional Services

This text of Arizona § 41-2577 (Progress payments; changed or additional work; attorney fees; definitions) is published on Counsel Stack Legal Research, covering Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ariz. Rev. Stat. Ann. § 41-2577 (2026).

Text

A.Progress payments may be made by this state to the contractor on the basis of a duly certified and approved estimate of the work performed during a preceding period of time as set by rule, except that a percentage of all estimates shall be retained as provided in section 41-2576. The progress payments shall be paid on or before fourteen days after the estimate of the work is certified and approved. The estimate of the work shall be deemed received by the owner on submission to any person designated by the owner for the submission, review or approval of the estimate of the work. An estimate of the work submitted under this section shall be deemed approved and certified seven days after the date of submission unless before that time the owner or owner's agent prepares and issues a specifi

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Arizona § 41-2577, Counsel Stack Legal Research, https://law.counselstack.com/statute/az/41-2577.