§ 41-2576 — Contract payment retention; partial payment

Arizona § 41-2576
JurisdictionArizona
Title 41Arizona Revised Statutes
Ch. 23ARIZONA PROCUREMENT CODE
Art. 5Procurement of Construction and Specified Professional Services

This text of Arizona § 41-2576 (Contract payment retention; partial payment) is published on Counsel Stack Legal Research, covering Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ariz. Rev. Stat. Ann. § 41-2576 (2026).

Text

A.Ten per cent of all construction contract payments shall be retained by this state as insurance of proper performance of the contract or, at the option of the contractor, a substitute security may be provided by the contractor in an authorized form pursuant to rules adopted by the director. The contractor is entitled to all interest from any such substitute security.
B.When the contract is fifty per cent completed, one-half of the amount retained or securities substituted pursuant to this section shall be paid to the contractor upon the contractor's request provided the contractor is making satisfactory progress on the contract and there is no specific cause or claim requiring a greater amount to be retained. After the contract is fifty per cent completed, no more than five per cent

Free access — add to your briefcase to read the full text and ask questions with AI

Nearby Sections

15
View on official source ↗

Cite This Page — Counsel Stack

Bluebook (online)
Arizona § 41-2576, Counsel Stack Legal Research, https://law.counselstack.com/statute/az/41-2576.